Generator

Generator Replacement Project

Budget

$756,500

Timeline

2025 – 2026

Contractor

Overseen by BRAA Management Team

Status

Completed

This project entails replacing the emergency generators for the Air Traffic Control Tower and the Airfield Electrical Vault. The project will also include replacing associated peripherals, cabling, monitoring equipment, fuel tanks, and containment equipment.

The airfield emergency generator was placed in service in 1996 and the Air Traffic Control Tower emergency generator was placed in service in 2005. As these units near and exceed 20 years in operation the required maintenance and upkeep have drastically increased and issues with reliability have been encountered. The project will also have an environmental benefit as newer generators have much lower emission levels.

Contractor

Overseen by BRAA Management Team.

Size/Scope

The project involves the complete replacement of emergency generator systems at two key locations: the Air Traffic Control Tower (ATCT) and the Airfield Electrical Vault.

Materials/Systems

Units, new cabling, monitoring equipment, fuel tanks, and containment systems.

Impact

Replaces units that have exceeded 20 years of service, reducing maintenance costs and eliminating reliability issues for critical safety equipment.